{"id":2504,"date":"2023-08-03T14:55:09","date_gmt":"2023-08-03T12:55:09","guid":{"rendered":"https:\/\/b8box.nl\/?p=2504"},"modified":"2025-10-13T17:52:45","modified_gmt":"2025-10-13T15:52:45","slug":"discount-for-delay-or-construction-time-extension","status":"publish","type":"post","link":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/","title":{"rendered":"Discount for delay or construction time extension?"},"content":{"rendered":"<p>Every project encounters events that lead to delays or disruptions. The responsibility of an event that cases delay may lie with the contractor, with the client or with both. To answer the question of responsibility, you will need to identify the causes of the delays and disruptions and individually understand their effect relative to the project schedule. Finally, you will need to assess the joint effect of the delays and disruptions. <\/p>\n<p>In this best practice, we outline the methodology for determining delay by cause (event). The aim is to objectively determine what part of a delay can be attributed to client or contractor.<\/p>\n<h3>Forensic Schedule Analysis<\/h3>\n<p>The methodology that you use to understand the effect of delays and disruptions is called Forensic Schedule Analysis. The American Association of Cost Engineers (AACE) has established an internationally recommended practice for delay analysis: AACE\u00ae International Recommended Practice No. 29R-03 Forensic Schedule Analysis (2011). Several methodologies are detailed in it.<\/p>\n<p><img decoding=\"async\" src=\"https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/08\/Planning.png\" alt=\"\" width=\"1425\" height=\"829\" class=\"alignnone size-full wp-image-1019\" srcset=\"https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/08\/Planning.png 1425w, https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/08\/Planning-1280x745.png 1280w, https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/08\/Planning-980x570.png 980w, https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/08\/Planning-480x279.png 480w\" sizes=\"(min-width: 0px) and (max-width: 480px) 480px, (min-width: 481px) and (max-width: 980px) 980px, (min-width: 981px) and (max-width: 1280px) 1280px, (min-width: 1281px) 1425px, 100vw\" \/><\/p>\n<h3>The methods<\/h3>\n<h4>As planned versus as-built<\/h4>\n<p>The as-planned versus as-built method compares baseline planning with as-built data, evaluating any impact on the critical path. The baseline schedule is the schedule that includes all the work according to the original contract (without additional and reduced work). Preferably, this baseline schedule is accepted by contractor and client. The as-built data can be a combination of planning updates, (inspection) reports, construction reports, photographs, and correspondence.<\/p>\n<h4>Time impact analysis<\/h4>\n<p>The time impact analysis method compares baseline planning with schedule updates. Changes to, for example, the construction sequence and critical path become clear when comparing multiple schedules.<\/p>\n<h4>Impacted as planned<\/h4>\n<p>The impacted as planned method adds the event to the schedule. If the completion date shifts after the event is included in the schedule, then it is caused by the event. If the delivery date does not shift, the event does not cause delay and is a disruption.<\/p>\n<h4>Collapsed as-built<\/h4>\n<p>The collapsed as-built method assumes the as-built schedule and removes the event from the schedule to determine the effect on the completion date. <\/p>\n<p>The figure below illustrates the comparison of as-planned versus as-built, as referred to in methodology 1.<\/p>\n<p><img decoding=\"async\" src=\"https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/08\/planning-as-built.jpg\" alt=\"\" width=\"1501\" height=\"401\" class=\"alignnone size-full wp-image-1020\" srcset=\"https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/08\/planning-as-built.jpg 1501w, https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/08\/planning-as-built-1280x342.jpg 1280w, https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/08\/planning-as-built-980x262.jpg 980w, https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/08\/planning-as-built-480x128.jpg 480w\" sizes=\"(min-width: 0px) and (max-width: 480px) 480px, (min-width: 481px) and (max-width: 980px) 980px, (min-width: 981px) and (max-width: 1280px) 1280px, (min-width: 1281px) 1501px, 100vw\" \/><\/p>\n<h3>Action plan<\/h3>\n<h5>1. Determine the methodology<\/h5>\n<p>The choice of methodology depends on the purpose of the analysis, the availability and reliability of the data, the size and complexity of the project. The methodology may also be prescribed in the contract.<\/p>\n<h5>2. Describe the event and determine the impact per event<\/h5>\n<p>In addition to the description, also indicate the day on which the event occurred and the end date of the event. You can get this information, for example, from construction reports or e-mail correspondence.*<\/p>\n<h5>3. Determine the impact of the joint events<\/h5>\n<p>If there is concurrence (competition) of delays, you should apply an offset. Ultimately, a contractor may have to pay a rebate on part of the delay and receive a construction time extension with reimbursement of costs for another part.<\/p>\n<p><span style=\"font-size: 16px;\">*To determine the impact of the event, you can use the following questions:<\/span><\/p>\n<ul style=\"font-size: 16px\">\n<li>Which activities cannot be performed as a result of the event?<\/li>\n<li>What activities can be performed in parallel with the event?<\/li>\n<li>Does the event lead to new activities?<\/li>\n<li>Does the event lead to the cancellation of activities?<\/li>\n<li>Does the event lead to adjustment of lead times of activities?<\/li>\n<li>Does the event lead to adjustment of the sequence of activities?<\/li>\n<\/ul>\n","protected":false},"excerpt":{"rendered":"<p>In this best practice, we outline the methodology for determining delay by cause (event).<\/p>\n","protected":false},"author":4,"featured_media":7505,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"_et_pb_use_builder":"","_et_pb_old_content":"","_et_gb_content_width":"","footnotes":""},"categories":[25,55,57],"tags":[],"class_list":["post-2504","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-insights-en","category-planning-management","category-project-management"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO Premium plugin v27.4 (Yoast SEO v27.4) - https:\/\/yoast.com\/product\/yoast-seo-premium-wordpress\/ -->\n<title>Discount for delay or construction time extension? - Vijverberg<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Discount for delay or construction time extension? | Vijverberg\" \/>\n<meta property=\"og:description\" content=\"In this best practice, we outline the methodology for determining delay by cause (event).\" \/>\n<meta property=\"og:url\" content=\"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/\" \/>\n<meta property=\"og:site_name\" content=\"Vijverberg\" \/>\n<meta property=\"article:published_time\" content=\"2023-08-03T12:55:09+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2025-10-13T15:52:45+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/07\/cropped-Vijverberg_VB.png\" \/>\n\t<meta property=\"og:image:width\" content=\"512\" \/>\n\t<meta property=\"og:image:height\" content=\"512\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"VijverbergB8\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"VijverbergB8\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"4 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/\"},\"author\":{\"name\":\"VijverbergB8\",\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/#\\\/schema\\\/person\\\/9dfd4c8039347a25c13eadf867baddea\"},\"headline\":\"Discount for delay or construction time extension?\",\"datePublished\":\"2023-08-03T12:55:09+00:00\",\"dateModified\":\"2025-10-13T15:52:45+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/\"},\"wordCount\":555,\"publisher\":{\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/vijverberg.com\\\/wp-content\\\/uploads\\\/2026\\\/01\\\/vijverberg_thumbnail.jpg\",\"articleSection\":[\"Insights\",\"Planning Management\",\"Project Management\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/\",\"url\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/\",\"name\":\"Discount for delay or construction time extension? - Vijverberg\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/vijverberg.com\\\/wp-content\\\/uploads\\\/2026\\\/01\\\/vijverberg_thumbnail.jpg\",\"datePublished\":\"2023-08-03T12:55:09+00:00\",\"dateModified\":\"2025-10-13T15:52:45+00:00\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/#primaryimage\",\"url\":\"https:\\\/\\\/vijverberg.com\\\/wp-content\\\/uploads\\\/2026\\\/01\\\/vijverberg_thumbnail.jpg\",\"contentUrl\":\"https:\\\/\\\/vijverberg.com\\\/wp-content\\\/uploads\\\/2026\\\/01\\\/vijverberg_thumbnail.jpg\",\"width\":1200,\"height\":630},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/insights-en\\\/discount-for-delay-or-construction-time-extension\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Discount for delay or construction time extension?\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/#website\",\"url\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/\",\"name\":\"Vijverberg | Helderheid en vertrouwen bij complexe bouwprojecten\",\"description\":\"Helderheid en vertrouwen bij complexe bouwprojecten\",\"publisher\":{\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/#organization\"},\"alternateName\":\"Vijverberg\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/#organization\",\"name\":\"Vijverberg\",\"alternateName\":\"Vijverberg\",\"url\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/vijverberg.com\\\/wp-content\\\/uploads\\\/2023\\\/11\\\/Vijverberg_logo_696x696.png\",\"contentUrl\":\"https:\\\/\\\/vijverberg.com\\\/wp-content\\\/uploads\\\/2023\\\/11\\\/Vijverberg_logo_696x696.png\",\"width\":696,\"height\":696,\"caption\":\"Vijverberg\"},\"image\":{\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.linkedin.com\\\/company\\\/vijverberg-management-consultants\\\/\",\"https:\\\/\\\/www.instagram.com\\\/vijverberg_projectmanagement\\\/\"],\"description\":\"Met ruim dertig jaar ervaring in projectmanagement en bouwgeschillen bij complexe projecten helpen wij opdrachtgevers om voor elke uitdaging praktische en duurzame oplossingen te vinden.\",\"email\":\"info@vijverberg.com\",\"telephone\":\"+31 (0)88 800 86 50\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/vijverberg.com\\\/en\\\/#\\\/schema\\\/person\\\/9dfd4c8039347a25c13eadf867baddea\",\"name\":\"VijverbergB8\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/7a194f4b4e776b144e2eab717d2b4e104172c2d903cabe3463b07e700c218ec7?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/7a194f4b4e776b144e2eab717d2b4e104172c2d903cabe3463b07e700c218ec7?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/7a194f4b4e776b144e2eab717d2b4e104172c2d903cabe3463b07e700c218ec7?s=96&d=mm&r=g\",\"caption\":\"VijverbergB8\"}}]}<\/script>\n<!-- \/ Yoast SEO Premium plugin. -->","yoast_head_json":{"title":"Discount for delay or construction time extension? - Vijverberg","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/","og_locale":"en_US","og_type":"article","og_title":"Discount for delay or construction time extension? | Vijverberg","og_description":"In this best practice, we outline the methodology for determining delay by cause (event).","og_url":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/","og_site_name":"Vijverberg","article_published_time":"2023-08-03T12:55:09+00:00","article_modified_time":"2025-10-13T15:52:45+00:00","og_image":[{"width":512,"height":512,"url":"https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/07\/cropped-Vijverberg_VB.png","type":"image\/png"}],"author":"VijverbergB8","twitter_card":"summary_large_image","twitter_misc":{"Written by":"VijverbergB8","Est. reading time":"4 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/#article","isPartOf":{"@id":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/"},"author":{"name":"VijverbergB8","@id":"https:\/\/vijverberg.com\/en\/#\/schema\/person\/9dfd4c8039347a25c13eadf867baddea"},"headline":"Discount for delay or construction time extension?","datePublished":"2023-08-03T12:55:09+00:00","dateModified":"2025-10-13T15:52:45+00:00","mainEntityOfPage":{"@id":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/"},"wordCount":555,"publisher":{"@id":"https:\/\/vijverberg.com\/en\/#organization"},"image":{"@id":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/#primaryimage"},"thumbnailUrl":"https:\/\/vijverberg.com\/wp-content\/uploads\/2026\/01\/vijverberg_thumbnail.jpg","articleSection":["Insights","Planning Management","Project Management"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/","url":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/","name":"Discount for delay or construction time extension? - Vijverberg","isPartOf":{"@id":"https:\/\/vijverberg.com\/en\/#website"},"primaryImageOfPage":{"@id":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/#primaryimage"},"image":{"@id":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/#primaryimage"},"thumbnailUrl":"https:\/\/vijverberg.com\/wp-content\/uploads\/2026\/01\/vijverberg_thumbnail.jpg","datePublished":"2023-08-03T12:55:09+00:00","dateModified":"2025-10-13T15:52:45+00:00","breadcrumb":{"@id":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/#primaryimage","url":"https:\/\/vijverberg.com\/wp-content\/uploads\/2026\/01\/vijverberg_thumbnail.jpg","contentUrl":"https:\/\/vijverberg.com\/wp-content\/uploads\/2026\/01\/vijverberg_thumbnail.jpg","width":1200,"height":630},{"@type":"BreadcrumbList","@id":"https:\/\/vijverberg.com\/en\/insights-en\/discount-for-delay-or-construction-time-extension\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/vijverberg.com\/en\/"},{"@type":"ListItem","position":2,"name":"Discount for delay or construction time extension?"}]},{"@type":"WebSite","@id":"https:\/\/vijverberg.com\/en\/#website","url":"https:\/\/vijverberg.com\/en\/","name":"Vijverberg | Helderheid en vertrouwen bij complexe bouwprojecten","description":"Helderheid en vertrouwen bij complexe bouwprojecten","publisher":{"@id":"https:\/\/vijverberg.com\/en\/#organization"},"alternateName":"Vijverberg","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/vijverberg.com\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/vijverberg.com\/en\/#organization","name":"Vijverberg","alternateName":"Vijverberg","url":"https:\/\/vijverberg.com\/en\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/vijverberg.com\/en\/#\/schema\/logo\/image\/","url":"https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/11\/Vijverberg_logo_696x696.png","contentUrl":"https:\/\/vijverberg.com\/wp-content\/uploads\/2023\/11\/Vijverberg_logo_696x696.png","width":696,"height":696,"caption":"Vijverberg"},"image":{"@id":"https:\/\/vijverberg.com\/en\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.linkedin.com\/company\/vijverberg-management-consultants\/","https:\/\/www.instagram.com\/vijverberg_projectmanagement\/"],"description":"Met ruim dertig jaar ervaring in projectmanagement en bouwgeschillen bij complexe projecten helpen wij opdrachtgevers om voor elke uitdaging praktische en duurzame oplossingen te vinden.","email":"info@vijverberg.com","telephone":"+31 (0)88 800 86 50"},{"@type":"Person","@id":"https:\/\/vijverberg.com\/en\/#\/schema\/person\/9dfd4c8039347a25c13eadf867baddea","name":"VijverbergB8","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/7a194f4b4e776b144e2eab717d2b4e104172c2d903cabe3463b07e700c218ec7?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/7a194f4b4e776b144e2eab717d2b4e104172c2d903cabe3463b07e700c218ec7?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/7a194f4b4e776b144e2eab717d2b4e104172c2d903cabe3463b07e700c218ec7?s=96&d=mm&r=g","caption":"VijverbergB8"}}]}},"_links":{"self":[{"href":"https:\/\/vijverberg.com\/en\/wp-json\/wp\/v2\/posts\/2504","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/vijverberg.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/vijverberg.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/vijverberg.com\/en\/wp-json\/wp\/v2\/users\/4"}],"replies":[{"embeddable":true,"href":"https:\/\/vijverberg.com\/en\/wp-json\/wp\/v2\/comments?post=2504"}],"version-history":[{"count":0,"href":"https:\/\/vijverberg.com\/en\/wp-json\/wp\/v2\/posts\/2504\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/vijverberg.com\/en\/wp-json\/wp\/v2\/media\/7505"}],"wp:attachment":[{"href":"https:\/\/vijverberg.com\/en\/wp-json\/wp\/v2\/media?parent=2504"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/vijverberg.com\/en\/wp-json\/wp\/v2\/categories?post=2504"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/vijverberg.com\/en\/wp-json\/wp\/v2\/tags?post=2504"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}